Manufacturing/Site preparation (Manufacture & Foundations 10-12 weeks)
From approval of drawings and placing the order, it takes 10-12 weeks for the manufacture of the modular building. During this period, any site excavations and foundations are completed, and the floor slab is laid to the design provided by PARASOL.
The foundation slab was designed by PARASOL and constructed by main framework contractor - Interserve Projects. Once the slab has been constructed, it must be left to 'cure' for at least 1 week before we can start on site. The main components are assembled in our warehouse before being delivered to site. |